Blogs

UAN11 May 27th

The network was operative with fixed and mobile nodes. Via the MOOS middleware, the Command and Control center was able to control the system, including sending commands to AUVs and requesting high rate sensor data. MOOS was operated in secure mode. Point to point connections were of varying quality due to environmental variation. Hence multihop routing proved useful.

Command and ControlCommand and ControlSignal received on the vertical arraySignal received on the vertical arrayFolaga deployment from Research vessel GunnerusFolaga deployment from Research vessel Gunnerus

UAN11 May 26th

The additional spare modem was deployed to replace Fixed Node 1. Full network was established, including Command and Control (C2). The Folaga was deployed from Research Vessel Gunnerus and followed by HiPAP acoustic positioning system. Gunnerus also served as an artificial AUV, with a cabled transducer at 20 m depth. In this way command and response exchange with the C2 could be followed in detail.

Network layoutNetwork layout Folaga deployed from RV GunnerusFolaga deployed from RV Gunnerus

UAN11 May 25th

Folagas at sea, diving. Relatively rough weather. A fixed node was lost during recovery. Will be replaced by a spare KM modem.

 

FolagaInWaves.JPG: Folaga at seaFolagaInWaves.JPG: Folaga at sea

UAN11 May 24th

Fixed nodes with temperature sensor chains were deployed. All network layers, from the physical acustic links via IP to the MOOS database were established.   A little wind and waves.Fixed node deployment: Subsurface float being attachedFixed node deployment: Subsurface float being attached

Last node completedLast node completed Following a FolagaFollowing a Folaga

UAN11 May 23rd

The Subsurface Telemetry Unit, with its vertical hydrophone array and fiberoptical cable to shore is installed and working. Acoustical connectivity tests have been completed. Folagas were at sea.

Optical cable being deployedOptical cable being deployed Subsurface Telemetry Unit with Kongsberg modem (yellow) on its way downSubsurface Telemetry Unit with Kongsberg modem (yellow) on its way down

UAN11 Engineering tests

Engineering tests are underway. After some delays caused by the transportation companies, all subsystems are being set up and functions verified.

Weather conditions are fair.

STU assembly on pierSTU assembly on pierFolaga first wet-testFolaga first wet-testC2 screen early snapshotC2 screen early snapshot

UAN10 - september 20th

RV Leonardo outside Pianosa IslandRV Leonardo outside Pianosa IslandSubsurface Telemetry Unit redeploymentSubsurface Telemetry Unit redeploymentPoint to Point transmissions, received signalsPoint to Point transmissions, received signalsAfter some maintenance to the Subsurface Telemetry Unit and attached vertical array it was successfully redeployed this morning. The weather was calm after a windy weekend. Point to point measuremens are currently being performed by transmitting signals from the R/V Leonardo and receiving on the vertical hydrophone array.

UAN10 - september 17th

Folaga deployment from RHIBFolaga deployment from RHIBFolagas with modemFolagas with modemKM modem on FologaKM modem on FologaFolaga AUVs where deployed today from a RHIB in parallel an underwater acoustic communication link was established between the Folagas and the master modem deployed from the R/V Leonardo. Various geometries where tested including fixed stations at the surface, the Folagas moving on the surface, Folagas deployed at various depths in a stationary position and a underwater moving scenario.

UAN10 - september 12th & 13th

FolagasFolagasFolagas and KM modemsFolagas and KM modemsFolagas in PortFolagas in PortRV LeonardoRV LeonardoLab workLab workDuring these days signals were transmitted from the RHIB and pier location, various resources both equipment and personnel can be seen in the pictures.

UAN10 - september 11th

Weather conditions did not permit the safe operation at sea nevertheless signal transmissions where performed from the pier using the Portable Acoustic Source Unit (PASU) and reception on the Subsurface Telemetry Unit (STU) 16 hydrophone vertical array. Initial results can be seen below.demodulated BPSK constellationdemodulated BPSK constellation